projects poland SANDEN MANUFACTURING 1+2

SANDEN MANUFACTURING 1+2

Client: SANDEN MANFUACTURING POLAND Sp. z o.o.

Total land area: 197,635m²
Effective floor area: 41,326m³
Building volume: 411,733m³
Building area: 39,044m²
Paved areas: 15,912m²
Lawns: 142,345m²
 

Stage 1 Construction time: April 2004 - March 2005
Stage 2 Construction time: January 2013 - July 2013

Location: Polkowice

Our scope of services: conceptual design, basic project evaluation, building permit design, working design, design supervision.

Stage I The production plant for air compressors (automobile industry) consists of the main hall with workshops and labs, and the office building.

Stage II encompasses a production hall adjacent on the whole length to the existing building, utility building and office building extension

pl | en | de

W ramach naszej witryny stosujemy pliki cookies w celu świadczenia Państwu usług na najwyższym poziomie, w tym w sposób dostosowany do indywidualnych potrzeb. Korzystanie z witryny bez zmiany ustawień dotyczących cookies oznacza, że będą one zamieszczane w Państwa urządzeniu końcowym. Możecie Państwo dokonać w każdym czasie zmiany ustawień dotyczących cookies.