Client:
HÄRTER TECHNIKA WYTŁACZANIA Sp. z o.o., Sp.k.

Total land area: 19,640m²
Effective floor area: 12,260m²
Building volume: 85,728m³
Building area: 8,988m²
Paved areas: 7,652m²
Lawns: 3,000m²

Location: Legnica Special Economic Zone
Construction time stage I: December 2004 – September 2005
Construction time stage II: December 2006 – July 2007

Stage I consisted in construction of a production facility comprising: a production-warehouse hall with an office building, a gate house, a utility building and a gas pressure reduction and measuring station.

During the second stage a new concrete reinforced production hall, adjacent to the existing one, was built, as well as a social building, a fire road and additional parking bays.

pl | en | de

W ramach naszej witryny stosujemy pliki cookies w celu świadczenia Państwu usług na najwyższym poziomie, w tym w sposób dostosowany do indywidualnych potrzeb. Korzystanie z witryny bez zmiany ustawień dotyczących cookies oznacza, że będą one zamieszczane w Państwa urządzeniu końcowym. Możecie Państwo dokonać w każdym czasie zmiany ustawień dotyczących cookies.