projects poland ROBERT BOSCH 1+2

ROBERT BOSCH 1+2

Client: ROBERT BOSCH Sp. z o.o.

Total land area: 198,000m²
Effective floor area stage 1: 16.970m²
Effective floor area stage 2: 1.344m²
Building area: 14,863m²
Building volume: 123,754m³
Paved areas: 14,800m²
Lawns: 164,660m²

Location:  Mirków, commune Długołęka

Design stage 1: july 2001 - february 2002
Construction stage 1: November 2001 - November 2002

Design stage 2: march 2006 - november 2006
Construction stage 2: november 2006 - july 2007

Our scope of services: building permit design, tender documentation, working design, design supervision.

The facility comprises a production hall, a two-storied office and social building, and a utility building.

pl | en | de

W ramach naszej witryny stosujemy pliki cookies w celu świadczenia Państwu usług na najwyższym poziomie, w tym w sposób dostosowany do indywidualnych potrzeb. Korzystanie z witryny bez zmiany ustawień dotyczących cookies oznacza, że będą one zamieszczane w Państwa urządzeniu końcowym. Możecie Państwo dokonać w każdym czasie zmiany ustawień dotyczących cookies.