  • News EN : We have begun designing the production facility of the coloured mixtures for SANOK RUBBER COMPANY in Sanok
  • News DE :

Client:
SANOK RUBBER COMPANY S.A.

Facility:
extension of the production plant

Location:
Sanok, Poland

News:
We have begun designing the production facility of the coloured mixtures for SANOK RUBBER COMPANY in Sanok.

Area of the production and warehouse buildings, staff/office building, utility building:
1st stage of construction:               3 915 m²
2nd stage of construction:             1 965 m²
3rd stage of construction:              2 750 m²

The scope of our services encompasses:
Conceptual design 1st stage + 2nd stage + 3rd stage of construction, building permit design, tender design and tender documentation 1st stage, design supervision at the construction site.